CHANGE ORDER #1-Final

‘08 CDBG

HANDICAP CURB REPLACEMENT

VILLAGE OF LEIPSIC

 

 

RESOLUTION

 

The Board of County Commissioners of Putnam County, Ohio, met in regular session on the 20th day of August, 2009, at the office of said Board with the following members present: Mr. John Love, Mr. Travis Jerwers and Mr. Vincent T. Schroeder.

 

          Mr.  Schroeder          moved the adoption of the following Resolution:

 

          WHEREAS, It has been recommended by Poggemeyer Design Group, Inc, engineers for the Handicap Curb Replacement – Village of Leipsic that the following change order be approved for Smith Paving & Excavating:

 

Balance of Bid Quantities

 

TOTAL INCREASE                                                                         $6,983.60

 

CHANGE IN CONTRACT PRICE:

Original contract price                 $48,234.40

Previous Change Orders               $         0.00    

Contract Price prior to this change orders   $48,234.40

Increase this change order              $  6,983.60

Contract price with all change orders     $55,218.00

 

      RESOLVED, The Board of County Commissioners does hereby approve the above change order as recommended by the engineer, Poggemeyer Design Group, Inc.

 

            Mr.  Love   seconded the motion and the roll being called upon its adoption, the vote resulted as follows: Mr. Love yes     Mr. Jerwers yes       Mr. Schroeder yes