CHANGE ORDER #1-Final

‘08 CDBG

NORTH CREEK ASPHALT PAVING PROGRAM

PALMER TOWNSHIP

 

 

RESOLUTION

 

The Board of County Commissioners of Putnam County, Ohio, met in regular session on the 10th day of November, 2009, at the office of said Board with the following members present: Mr. John Love, Mr. Travis Jerwers and Mr. Vincent T. Schroeder.

 

          Mr. Love           moved the adoption of the following Resolution:

 

          WHEREAS, It has been recommended by the Putnam County Engineer’s office, engineers for the North Creek Asphalt Paving Program – Palmer Township that the following change order be approved for Ward Construction Company:

 

Adjust original contract quantities of those items 100% complete, to the quantities actually performed and add additional items.

 

TOTAL INCREASE                                                                         $3,030.28

 

CHANGE IN CONTRACT PRICE:

Original contract price                 $62,809.00

Previous Change Orders               $         0.00    

Contract Price prior to this change orders   $62,809.00

Increase this change order              $  3,030.28

Contract price with all change orders     $65,839.28

 

      RESOLVED, The Board of County Commissioners does hereby approve the above change order as recommended by the engineer, Putnam County Engineer.

 

            Mr. Schroeder    seconded the motion and the roll being called upon its adoption, the vote resulted as follows:  Mr. Love yes       Mr. Jerwers yes     Mr. Schroeder yes